Design Phase of the Spenard Road Reconstruction Project
Benson Boulevard to Chester Creek

Schedule.

  • Preliminary Engineering and Environmental Approval - 3rd quarter 2005 to 4th quarter 2006
  • Final Design - January 2006 through December 2009
  • Utilities - January 2006 through December 2009
  • Bid - January through February 2009
  • Construction - 2nd quarter 2009 through 4th quarter 2011